Stucco calculator

Enter the wall area and what you are plastering over. You get the coats, the thickness of each, and the bags of base coat and finish coat separately — at the honest end of the manufacturer’s coverage range.

Coverage from the QUIKRETE data sheetThicknesses from IRC Table R702.1(1) and ASTM C926Coat by coat, not one lump

Inputs

Wall area
sq ft
sq ft
Subtracted from the wall area.
Sets the number of coats and the thickness of each.
Coverage to use
ft
For weep screed. Leave at 0 to skip.

Result

Bags of stucco
—

Coverage per 80 lb bag of base coat

QUIKRETE’s Scratch and Brown Base Coat data sheet publishes two things that fit together exactly: a yield of 0.75 ft³ per 80 lb bag, and a coverage range at three thicknesses. Divide the yield by the thickness and you land on the top of every published range. Multiply that by five sixths and you land on the bottom of every one.

ThicknessYield ÷ thicknessLess the allowanceAs publishedBags per 100 sq ft
1/4 in3630—4
3/8 in242020–245
1/2 in181515–187
5/8 in14.412—9
3/4 in121010–1210
7/8 in10.38.6—12

The greyed column is the arithmetic maximum — every cubic foot of mix landing on the wall and staying there. The bold column takes off the 16.7% the manufacturer’s own range allows for waste and for what the lath keys swallow behind the plane you are measuring. Rows without a published range are the same arithmetic at thicknesses the data sheet does not print.

Coats and thickness, by what you are plastering over

BackingCoatsFirstSecondThirdTotal
Metal or wire lath over framing33/8 in3/8 in1/8 in7/8 in
Unit masonry21/2 in1/8 in—5/8 in
Cast-in-place concrete21/2 in1/8 in—5/8 in
One-coat system over lath21/4 in1/8 in—3/8 in

Three coats over metal lath, two over masonry, concrete or gypsum (IRC R703.6.2). The 7/8 in over wire lath is measured from the face of the support, so the lath itself sits inside that dimension. For unit masonry the two documents differ: ASTM C926 gives 5/8 in nominal for two-coat work, the IRC table sets the minimum at 1/2 in. This page uses the ASTM figure, which is the thicker of the two.

Why most stucco calculators under-order by 20%. A coverage range of “20 to 24 square feet” is not a measurement spread; it is the theoretical yield at one end and a flat 16.7% allowance at the other. Quote the 24 and a 1,000 sq ft three-coat job needs 99 bags. Quote the 20, which is what actually goes on a wall, and it needs 115. That is 16 bags, and the pallet does not turn up on its own halfway through a scratch coat.

A three-coat job is three different orders

The scratch and brown coats are the same product at 3/8 in each. The finish coat is a different bag entirely, goes on at 1/8 in, and covers 70 sq ft a bag instead of 20. Adding the thicknesses up and dividing once gives you the wrong mix of products even when the total weight is close.

For 1,000 sq ft over lath that is 50 bags of base coat for the scratch, 50 more for the brown and 15 of finish coat. 115 bags in total, 9,200 lb, which is 4.6 tons of material going up a wall by hand, and about 550 quarts of water to mix the base coats.

The same wall over unit masonry drops to 82 bags, because the base coat is one 1/2 in pass instead of two at 3/8 in. A proprietary one-coat system over lath comes to 57.

Three code points that fail inspections. Two layers of water-resistive barrier behind the lath, not one (IRC R703.7.3; CBC 2510.6), each a separate continuous plane. A weep screed of at least 0.019 in (No. 26 galvanised) with a 3-1/2 in vertical flange, set no less than 4 in above earth and 2 in above paving, with the barrier lapping the flange and the lath terminating on it. And the scratch coat moist-cured 48 hours with a 48-hour wait before the brown coat goes on.

What this does not do

  • It does not price the job. Stucco is quoted per square foot installed and the rate moves with region, height, access and finish texture. Bags are the part that can be counted honestly.
  • It does not count lath, screed or fasteners. Those come off a takeoff of the elevations, not off an area figure, and the accessory list is where stucco estimates usually go wrong.
  • It assumes a flat wall. Bands, reveals, arches and heavy textures all use more, and a sprayed finish wastes more than a hand-applied one.
  • Coverage is one manufacturer’s. The yield and the range here are QUIKRETE’s. Other brands publish their own and they are not identical; the arithmetic for converting a yield into coverage is the same whichever bag you buy.
  • One-coat systems are proprietary and installed under their own evaluation report. The thickness here is indicative; the report for the actual product governs.

Questions

How many bags of stucco do I need for 1,000 square feet?

For a three-coat job over metal lath, about 115 eighty-pound bags: 50 for the scratch coat, 50 for the brown coat and 15 of finish coat. That is roughly 4.6 tons. Over unit masonry it drops to about 82 bags, because the base coat is one half-inch pass instead of two three-eighths passes. Those figures use the realistic end of the published coverage range.

How much does an 80 lb bag of stucco cover?

20 to 24 square feet at 3/8 inch, 15 to 18 at 1/2 inch, and 10 to 12 at 3/4 inch. The high number in each pair is the bag's theoretical yield of 0.75 cubic feet divided by the thickness, with nothing lost. The low number is exactly five sixths of that, which is the allowance for waste and for the material that disappears into the lath keys. Order to the low number.

How thick should stucco be?

Over metal or wire lath, 7/8 inch in three coats: 3/8 scratch, 3/8 brown and 1/8 finish, measured from the face of the support. Over unit masonry or concrete it is two coats, 5/8 inch nominal under ASTM C926, with the IRC table allowing a minimum of 1/2 inch on masonry. Proprietary one-coat systems are thinner and follow their own evaluation report.

Is stucco two coats or three?

Three over metal lath, two over masonry, concrete or gypsum board. That is IRC R703.6.2. The two-coat case works because the backing is already solid and does not need a scratch coat keyed into lath to hold the rest. A one-coat system is a different thing again: a proprietary fibreglass-reinforced base plus a finish, approved under an evaluation report.

How long between stucco coats?

The scratch coat is moist-cured for a minimum of 48 hours and then left a further 48 hours before the brown coat goes on. The brown coat is not applied until the scratch is rigid enough to take it without deforming. The finish coat needs fog misting or similar curing to stop it drying too fast, which matters most in wind, low humidity or above 90°F.

Do I need one layer of building paper under stucco or two?

Two. The code calls for two layers of Grade D paper behind the lath, installed so each forms a separate continuous drainage plane. There is an exception where a single layer is separated from the stucco by a substantially non-water-absorbing layer or a designed drainage space. This is one of the most common stucco inspection failures, and it costs nothing to get right.