Asphalt calculator
Add the areas to pave and the finished thickness. You get the tons of asphalt to order at the industry's standard 110 lb per square yard per inch, the laying thickness and lifts, the gravel base, and the cost at your supplier's price.
Inputs
Result
- Area
- 600 sq ft 66.7 yd²
- Tons before waste
- 11.00
- Tons to order
- 11.6 23,100 lb
- Compacted volume
- 5.56 yd³
- Laying (screed) thickness
- about 3-3/4 in 1.25 x compacted
- Thinnest lift for this mix
- 2 in 4 x stone size
Most plants sell by the ton, with a minimum load; ask about a small-load charge for driveway jobs. Hot mix has to be placed and rolled while hot, so order what the crew can lay that day.
Asphalt coverage by thickness
At 110 lb per square yard per inch of compacted thickness, before waste.
| Thickness | lb per ft² | ft² per ton | Tons per 1,000 ft² |
|---|---|---|---|
| 1.5 in | 18.3 | 109 | 9.17 |
| 2 in | 24.4 | 82 | 12.22 |
| 2.5 in | 30.6 | 65 | 15.28 |
| 3 in | 36.7 | 55 | 18.33 |
| 4 in | 48.9 | 41 | 24.44 |
| 5 in | 61.1 | 33 | 30.56 |
| 6 in | 73.3 | 27 | 36.67 |
How it is worked out
A driveway 12 ft wide and 50 ft long is 600 ft², or 66.7 square yards. At 3 in compacted: 66.7 x 3 x 110 = 22,000 lb, or 11 tons; 11.6 tons with 5% extra. The paver lays it about 3-3/4 in thick and the roller brings it down to 3.
Where 110 lb per square yard per inch comes from
It is the typical spread rate for compacted hot mix asphalt that paving contractors and asphalt associations use for estimating, the figure the Minnesota Asphalt Pavement Association's calculator and Asphalt magazine's rules of thumb give. It is the same as about 147 lb per cubic foot, or a little under 2 tons per cubic yard compacted. Mixes vary slightly; if your plant gives you its own figure, use that.
How thick should an asphalt driveway be?
The Illinois Asphalt Pavement Association recommends:
- On a gravel base: 3 in of asphalt over 6 to 8 in of compacted aggregate.
- Full-depth asphalt: 4 in may be adequate, but 5 or 6 in makes a stronger driveway, placed in lifts of 1-1/2 in compacted.
- Overlay of an existing driveway: a surface course 1-1/2 to 2 in thick.
NAPA's research puts 1 in of asphalt as equivalent to about 3 in of aggregate base.
Lifts
Thick pavements are laid in layers, or lifts, each rolled before the next. A lift should be at least four times the largest stone size in the mix: 2 in for a common 1/2 in surface mix, 3 in for a 3/4 in base mix. Thinner lifts tear and do not compact. The paver's screed is set about 1.25 times the planned compacted thickness, since rolling compacts the mat by about a fifth.
For the gravel base in tons, use the gravel calculator; for a concrete driveway instead, the concrete calculator.
Questions
How many tons of asphalt do I need?
Multiply the area in square yards by the compacted thickness in inches and by 110 lb, then divide by 2,000. A 600 ft² driveway at 3 in needs 11 tons, about 11.6 with 5% waste.
How much does a ton of asphalt cover?
About 82 ft² at 2 in thick, 55 ft² at 3 in and 41 ft² at 4 in, at 110 lb per square yard per inch.
How many square yards does a ton of asphalt cover?
2,000 / (110 x thickness): about 9.1 yd² at 2 in, 6.1 yd² at 3 in and 4.5 yd² at 4 in.
How much does a cubic yard of asphalt weigh?
About 3,960 lb, just under 2 tons, compacted: 110 lb per square yard per inch is 146.7 lb per cubic foot.
How thick should an asphalt driveway be?
3 in of asphalt over 6 to 8 in of compacted gravel, or 4 to 6 in of full-depth asphalt in 1-1/2 in lifts, per the Illinois Asphalt Pavement Association. An overlay is 1-1/2 to 2 in.
How many tons of asphalt for a 2-car driveway?
A 20 x 40 ft driveway is 800 ft², or 88.9 yd². At 3 in: 88.9 x 3 x 110 / 2,000 = 14.7 tons, about 15.4 with 5% extra.
Sources and method: Minnesota Asphalt Pavement Association and Asphalt magazine for spread rates; Illinois Asphalt Pavement Association for driveway build-ups. The full list, with the calculators that use each source, is on the sources page.
Sources
- Minnesota and Illinois Asphalt Pavement Associations, and Asphalt magazine (spread rates and driveway build-ups). Industry references.
More Concrete calculators
Excavation, trench & cut-and-fill calculator
Dirt to dig for a trench or a pit with the walls laid back to the OSHA slope, what it swells to on the truck, and the cut-and-fill balance.
Rebar calculator
Rebar for a slab grid: bars each way, lap splices, 20 ft sticks, weight, ties and chairs, plus a rebar weight calculator.
Mortar calculator
Bags of mortar mix for a brick or block wall, from the wall area or the number of units, at Quikrete's published yields.
Self-leveling concrete calculator
How many bags of self-leveler a floor needs, for Quikrete, LevelQuik, Henry, Ardex, Sakrete and Rapid Set, at any thickness.
Concrete calculator
Cubic yards and 40, 60 or 80 lb bags for a slab, footing, post holes or steps, with waste and the ready-mix order.
Concrete block calculator
Blocks or bricks for a wall, with mortar bags, core grout and courses, net of doors and windows.
Stucco calculator
Bags of base coat and finish coat for a three-coat or two-coat stucco job, at the honest end of the published coverage.