RoughInSizing calculators for the trades

Excavation calculator

Enter the hole. You get the dirt in the ground, what it swells to once it is dug, the weight, and how many truck loads that really is — with the walls laid back to the OSHA slope for your soil.

OSHA 1926 Subpart P Table B-1Caterpillar bank and loose densitiesVolume and payload both checked

Inputs

What are you digging?
ft
ft
The bucket width, not the top of the hole.
ft
in
For the backfill figure. 0 if there is no pipe.
in
Stone below the pipe. 0 if none.
Sets the swell and the weight.
From the competent person on site.
Untick for a vertical cut (shoring or a trench box).
%
0 for a struck load. 10–15% if it is heaped.

Result

Excavation
—
Loads by truck type
Truckyd³TonsLoadsLimited by
Pickup truck (1/2 ton)20.8205weight
Pickup truck (1 ton dump)32.077weight
Single-axle dump truck77.022weight
Tandem-axle dump truck1215.013volume
Tri-axle dump truck1621.010volume
Dump trailer (end dump)2225.07volume

OSHA maximum allowable slopes

From 29 CFR 1926 Subpart P, Appendix B, Table B-1, for an excavation less than 20 ft deep. The last column is how far back the top of the wall moves for every foot of depth.

Soil or rockSlope (H:V)AngleSet back per ft of depth
Stable rockVertical90°— ft
Type A, 12 ft or less (short term)1/2:163°0.5 ft
Type A3/4:153°0.75 ft
Type B1:145°1 ft
Type C1-1/2:134°1.5 ft
A protective system is required at 5 ft and deeper (1926.652(a)(1)) — slope it, shore it or use a trench box. Over 20 ft the design has to come from a registered professional engineer. Which soil type you have is a call for the competent person on site, not for a web page.

Trench volume chart, 100 ft of 2 ft wide trench

Cubic yards in the ground for 100 linear feet, bottom width 2 ft, walls laid back to each OSHA slope. Multiply by your own length over 100.

DepthStable rockType A, 12 ft or less (short term)Type AType BType C
2 ft14.822.225.929.637.0
3 ft22.238.947.255.672.2
4 ft29.659.374.188.9118.5
5 ft37.083.3106.5129.6175.9
6 ft44.4111.1144.4177.8244.4
8 ft59.3177.8237.0296.3414.8
10 ft74.1259.3351.9444.4629.6
12 ft88.9355.6488.9622.2888.9

Top width at the surface

How wide the hole is at grade, from a 2 ft bottom. This is the number that decides whether it fits between the house and the fence.

DepthStable rockType A, 12 ft or less (short term)Type AType BType C
2 ft2 ft4 ft5 ft6 ft8 ft
3 ft2 ft5 ft6.5 ft8 ft11 ft
4 ft2 ft6 ft8 ft10 ft14 ft
5 ft2 ft7 ft9.5 ft12 ft17 ft
6 ft2 ft8 ft11 ft14 ft20 ft
8 ft2 ft10 ft14 ft18 ft26 ft
10 ft2 ft12 ft17 ft22 ft32 ft
12 ft2 ft14 ft20 ft26 ft38 ft

Swell and weight by soil

Loose and bank densities and load factors as published in the Caterpillar Performance Handbook tables. Swell = (1 ÷ load factor − 1); the last column is how many loose yards one bank yard becomes.

MaterialLoose, lb/yd³Bank, lb/yd³Load factorSwellLoose yd³ per bank yd³
Clay, natural bed2,8003,4000.8222%1.22
Clay, dry2,5003,1000.8123.5%1.235
Clay, wet2,8003,5000.8025%1.25
Clay and gravel, dry2,4002,8000.8517.6%1.176
Clay and gravel, wet2,6003,1000.8517.6%1.176
Earth, dry packed2,5503,2000.8025%1.25
Earth, wet excavated2,7003,4000.7926.6%1.266
Earth, loam2,1002,6000.8123.5%1.235
Gravel, pit run3,2503,6500.8912.4%1.124
Gravel, dry2,5502,8500.8912.4%1.124
Gravel, wet (1/4–2 in)3,4003,8000.8912.4%1.124
Sand, dry2,4002,7000.8912.4%1.124
Sand, damp2,8503,2000.8912.4%1.124
Sand, wet3,1003,5000.8912.4%1.124
Sand and clay2,7003,4000.7926.6%1.266
Sand and gravel, dry2,9003,2500.8912.4%1.124
Sand and gravel, wet3,4003,7500.919.9%1.099
Crushed stone2,7004,5000.6066.7%1.667
Topsoil1,6002,3000.7042.9%1.429

Hauling units

Struck body volume and legal payload. Typical figures — weigh your own truck, because bodies and axle ratings vary. The calculator checks both and tells you which one runs out first.

TruckStruck yd³Payload, tons
Pickup truck (1/2 ton)20.8
Pickup truck (1 ton dump)2.52
Single-axle dump truck77
Tandem-axle dump truck1215
Tri-axle dump truck1621
Dump trailer (end dump)2225

Bank, loose and compacted

Earthwork is quoted in three different cubic yards and mixing them up is the usual way an estimate goes wrong.

  • Bank (BCY) — the soil as it sits in the ground, undisturbed. This is what you measure off the drawing and what you are paid to excavate.
  • Loose (LCY) — once it is dug it swells, because there is now air between the lumps. This is what sits on the truck and what you order haulage by.
  • Compacted (CCY) — rolled back into a fill, it ends up denser than it was in the bank. Fill is specified compacted, so you always need more bank than the fill volume suggests.

A worked trench: 100 ft long, 2 ft wide, 4 ft deep, Type C soil laid back at 1-1/2:1. Vertical, that hole is 29.6 yd³. Sloped, the top opens out to 14 ft wide and the hole becomes 118.5 yd³ — exactly 4 times the dirt. That is the number most trench calculators leave out, and in loam it is the difference between 4 tandem loads and 13.

Why weight beats volume on wet ground

A tandem-axle truck holds about 12 yd³ and may carry about 15 tons. Those two limits do not run out together. 100 bank yd³ of dry sand becomes 112.4 loose yd³ weighing 134.8 tons — 10 loads, and volume is what fills the truck. The same 100 yd³ of wet clay becomes 125 loose yd³ weighing 175 tons, which is 12 loads because the truck is out of weight at 11.7 loads while the body is only 10.4 full. Price the wet job by volume and you under-bid the haulage.

Cut and fill

Fill is specified compacted, and compacting shrinks it, so the bank volume you have to find is the fill divided by (1 − shrinkage). Cutting 500 yd³ and filling 300 yd³ at 15% shrinkage needs 352.9 yd³ of bank for the fill, which leaves 147.1 yd³ to export — 181.6 loose yd³ on the truck, or 16 loads. If the fill had been larger than the cut, the same arithmetic runs the other way and you are buying material in.

Shrinkage is the one figure on this page that does not come from a published table, because it depends on the compaction specified and on the material. Take it from the geotechnical report. 10–25% covers most common soils, and Caterpillar's single published compacted figure — sand and clay at 4,050 lb/yd³ against 3,400 bank — works out at 16%.

What this does not do

It assumes a prismatic hole with a flat bottom and uniform depth. Real sites are not flat: a proper cut-and-fill takes grid or cross-section levels and sums them. Use this for a trench, a footing, a pad or a first-pass balance, not in place of a survey. It also takes no account of groundwater, rock, existing services or working room beyond the slope.

Questions

How many cubic yards is a 100 ft trench?

With a 2 ft bottom and vertical walls, 100 ft of trench is 14.8 yd³ at 2 ft deep, 29.6 yd³ at 4 ft and 44.4 yd³ at 6 ft. Lay the walls back for Type C soil and the same trench becomes 118.5 yd³ at 4 ft deep, because the top opens out to 14 ft wide.

How do I calculate trench volume with sloped sides?

The cross-section is a trapezoid, so volume = length × depth × (bottom width + depth × slope), where slope is the horizontal run per foot of depth: 0.75 for Type A, 1 for Type B, 1.5 for Type C. A 1-1/2:1 wall moves the top back 1.5 ft for every foot of depth, on both sides.

What is soil swell?

Soil takes up more room once it is dug, because there is now air between the lumps. Dry sand swells about 12.4%, loam about 23.5%, wet clay about 25% and crushed stone about 66.7%. So 100 yd³ dug out of the ground is 125 yd³ on the truck if it is wet clay.

How many truck loads is 100 cubic yards of dirt?

It depends on the soil and the truck, and on which limit runs out first. 100 bank yd³ of dry sand is 112.4 loose yd³ at 134.8 tons, so 10 tandem loads. The same 100 yd³ of wet clay is 125 loose yd³ at 175 tons, which is 12 loads — the truck hits its payload before the body is full.

How deep can a trench be before it needs shoring?

5 ft. OSHA 1926.652(a)(1) requires a protective system at 5 ft or deeper unless the excavation is entirely in stable rock — slope it back, shore it, or use a trench box. Over 20 ft the protective system has to be designed by a registered professional engineer.

What slope is required for Type C soil?

1-1/2:1, which is 34° from horizontal: the top of the wall sits 1.5 ft back from the bottom for every foot of depth. Type B is 1:1 (45°), Type A is 3/4:1 (53°), and Type A at 12 ft or less may be cut at 1/2:1 (63°) short term. Stable rock may be vertical.

What is the difference between bank, loose and compacted cubic yards?

Bank is the soil undisturbed in the ground, which is what you measure off the drawing. Loose is after digging, swollen, which is what rides on the truck. Compacted is after rolling, denser than bank, which is how fill is specified. One bank yard of loam is about 1.24 loose yards but only about 0.85 compacted yards.

How much more do I need to dig for a sloped trench?

At 4 ft deep with a 2 ft bottom, laying the walls back multiplies the dirt by about 2.5 for Type A, 3 for Type B and 4 for Type C. It gets worse with depth, because the extra is proportional to the depth squared.

How do I work out cut and fill?

Compare the cut, measured bank, with the bank volume the fill needs. Fill is specified compacted, and compaction shrinks it, so bank needed = fill ÷ (1 − shrinkage). Cutting 500 and filling 300 yd³ at 15% shrinkage needs 352.9 yd³ for the fill, so 147.1 yd³ is surplus and goes off site.

Why do swell figures differ between sources?

Because soil is not a manufactured product. These tables use the Caterpillar Performance Handbook load factors, which give wet clay about 25% swell. Other references print 40% for clay. The honest answer is that the figure depends on the moisture, the grain size and how the ground has been compacted, so the tables are a starting point and the site is the authority.

Does the spoil pile fit back in the trench?

No, and that catches people out. The spoil is loose and the trench is bank-measured, so a trench backfilled with its own spoil leaves a surplus of 10–25% sitting on the surface before compaction, more for topsoil or stone. Once it is compacted back it usually ends up slightly short, which is why fill is ordered on the compacted figure.

Sources and method: OSHA 29 CFR 1926 Subpart P, Appendix B, Table B-1 for trench slopes; Caterpillar Performance Handbook for swell and loose density. The full list, with the calculators that use each source, is on the sources page.

Sources

More Concrete calculators

Other trades