Concrete block calculator
Enter the wall's length and height. You get the blocks to order, the courses, the bags of mortar and, if the cores are grouted, the grout in yards and bags.
Inputs
Result
- Wall area
- 160 sq ft
- Courses
- 6
- Blocks per course
- 30.0
- Blocks, exact
- 180.0
- With 5% waste
- 189
- Mortar, 80 lb bags
- 14
- Core grout
- 1.80 cu yd
- Grout volume
- 48.6 cu ft
- As 80 lb bags
- 81
Block fill from the block makers’ published yield table. Over a yard of grout is usually pumped or delivered as ready-mix masonry grout rather than mixed from bags.
Blocks per square foot
How many units cover a square foot of wall, with standard 3/8 in mortar joints.
| Unit | Face, nominal | Per sq ft | Per 80 lb mortar bag |
|---|---|---|---|
| Concrete block (CMU) | 8 x 16 in | 1.125 | 13 |
| Modular brick | 2-2/3 x 8 in | 6.75 | 37 |
How it is worked out
A standard block is 7-5/8 by 15-5/8 in on its face. With a 3/8 in joint it takes up 8 by 16 in of wall, 128 sq in, so 144 / 128 = 1.125 blocks fill a square foot. A 40 ft wall 4 ft high is six courses of 30 blocks: 180 blocks, 189 with 5% waste, and 14 bags of mortar.
Concrete block fill: grout in the cores
Reinforced block walls have steel in some cores, and those cores are filled with grout — “block fill” or “core fill”. How much depends on the block width and how many cells are filled. The calculator uses the yield table block makers publish (Westbrook Concrete Block and Fairbanks Materials print the same one): a cubic yard fills about 100 standard 8 in blocks when every cell is grouted. Solid-grouting the 40 ft x 4 ft wall above, 180 blocks, takes 1.80 cubic yards, or 48.6 cu ft.
| Block | Cells grouted | Cu yd per 100 sq ft of wall | Cu yd per 100 blocks | Blocks per cu yd | 80 lb bags per 100 blocks |
|---|---|---|---|---|---|
| 6 in | All cells | 0.93 | 0.83 | 120 | 38 |
| 6 in | 16 in on centre | 0.55 | 0.49 | 205 | 23 |
| 6 in | 24 in on centre | 0.42 | 0.37 | 270 | 17 |
| 6 in | 32 in on centre | 0.35 | 0.31 | 320 | 14 |
| 8 in | All cells | 1.12 | 1.00 | 100 | 45 |
| 8 in | 16 in on centre | 0.65 | 0.58 | 171 | 27 |
| 8 in | 24 in on centre | 0.50 | 0.44 | 225 | 20 |
| 8 in | 32 in on centre | 0.43 | 0.38 | 267 | 18 |
| 10 in | All cells | 1.30 | 1.23 | 80 | 56 |
| 10 in | 16 in on centre | 0.82 | 0.75 | 137 | 34 |
| 10 in | 24 in on centre | 0.63 | 0.56 | 180 | 26 |
| 10 in | 32 in on centre | 0.53 | 0.47 | 214 | 22 |
| 12 in | All cells | 1.73 | 1.54 | 65 | 70 |
| 12 in | 16 in on centre | 1.01 | 0.90 | 111 | 41 |
| 12 in | 24 in on centre | 0.76 | 0.68 | 146 | 31 |
| 12 in | 32 in on centre | 0.64 | 0.57 | 174 | 26 |
Standard two-cell 8 x 16 in block, “estimated yields” as the block makers put it; partly grouted walls take a little more than a straight share of the solid figure in this table. Bags are 80 lb bags of concrete or grout mix at 0.6 cu ft each, to show why more than about half a yard is ordered as ready-mix or pumped. 4 in block and cells at 48 in on centre are not in the table; the calculator uses half the block’s volume for those.
Masonry grout is a fluid mix to ASTM C476, coarse or fine, not ordinary concrete, and add 10% or so for waste. Check what your plans call for. This is not tile grout: for that, use the grout calculator.
Questions
How many blocks are in a square foot?
1.125 standard 8 x 16 in concrete blocks, counting the mortar joint. 100 sq ft of wall takes 112.5 blocks before waste.
How many cinder blocks do I need for a 4 ft wall?
Six courses of 8 in block. Each course takes 0.75 blocks per foot of wall, so a 40 ft wall needs 30 a course and 180 in all, plus about 5% for breakage.
How many blocks does a bag of mortar lay?
Quikrete says up to 13 standard 8 x 8 x 16 in blocks per 80 lb bag of Mortar Mix, or up to 37 bricks. That makes about 8 bags per 100 blocks.
How much grout fills a concrete block?
About 0.27 cu ft for each 8 in block if every core is filled: a cubic yard fills about 100 blocks, by the yield table block makers publish. A 12 in block takes about 0.42 cu ft, a 6 in block 0.22.
How much concrete does it take to fill cinder blocks?
About 1 cubic yard per 100 standard 8 in blocks with every cell filled, 1.54 yards per 100 blocks of 12 in and 0.83 of 6 in. With cells at 16 in on centre, 0.58 yards per 100 blocks of 8 in. That is roughly 45 80 lb bags per 100 solid-grouted 8 in blocks, which is why block fill is usually ordered as ready-mix grout.
How many blocks does a yard of grout fill?
About 100 standard 8 in blocks with every cell filled, 65 of 12 in, 80 of 10 in and 120 of 6 in. Grouting cells at 16 in on centre, a yard goes about 171 blocks of 8 in.
How many bricks per square foot?
6.75 modular bricks, laid with 3/8 in joints. A 100 sq ft wall takes 675 bricks before waste.
Sources
More Concrete calculators
Excavation, trench & cut-and-fill calculator
Dirt to dig for a trench or a pit with the walls laid back to the OSHA slope, what it swells to on the truck, and the cut-and-fill balance.
Asphalt calculator
Tons of hot mix asphalt for a driveway, path or lot, at the industry's 110 lb per square yard per inch, with lifts, base and cost.
Rebar calculator
Rebar for a slab grid: bars each way, lap splices, 20 ft sticks, weight, ties and chairs, plus a rebar weight calculator.
Mortar calculator
Bags of mortar mix for a brick or block wall, from the wall area or the number of units, at Quikrete's published yields.
Self-leveling concrete calculator
How many bags of self-leveler a floor needs, for Quikrete, LevelQuik, Henry, Ardex, Sakrete and Rapid Set, at any thickness.
Concrete calculator
Cubic yards and 40, 60 or 80 lb bags for a slab, footing, post holes or steps, with waste and the ready-mix order.
Stucco calculator
Bags of base coat and finish coat for a three-coat or two-coat stucco job, at the honest end of the published coverage.